WHS Management Plan for Construction in NSW: What to Include (With Example)

Two safety consultants in hard hats and hi-vis vests reviewing a clipboard on a construction site

Updated for the NSW WHS Regulation 2025

A WHS management plan is the site-wide safety plan the principal contractor must prepare before work starts on a NSW construction project worth $250,000 or more. It sets out who is responsible for safety, how contractors coordinate, how incidents are managed, the site rules, and how Safe Work Method Statements (SWMS) are collected and reviewed.

For builders, a good WHS management plan is more than a box to tick. It’s the practical framework for running safety across the site, keeping subcontractors coordinated and making sure everyone knows their responsibilities.

Under the NSW Work Health and Safety Regulation 2025, which started on 22 August 2025, principal contractors must prepare, communicate, review and keep a written WHS management plan for construction projects.

This guide explains when you need a WHS management plan, what it must include, how to put one together and what a practical example looks like.

What Is a WHS Management Plan?

A Work Health and Safety (WHS) management plan is a written document that explains how health and safety will be managed across a construction project.

It sets up the site-wide arrangements that let the principal contractor, subbies, workers and other businesses on site coordinate their safety responsibilities.

A construction WHS management plan usually explains:

  • Who is responsible for safety on site
  • How contractors and subcontractors will communicate and coordinate their work
  • What happens when an incident occurs
  • The site-specific safety rules everyone must follow
  • How SWMS are collected, assessed, monitored and reviewed

The plan should reflect the actual job. A generic document that lists safety policies without explaining how they work on site won’t do the job.

The term “WHS management plan” is also used for a company-wide safety document. This article is about the construction project WHS management plan required in NSW.

Does Your Construction Project Need a WHS Management Plan? The $250,000 Test

In NSW, a construction project is one where the cost of the construction work is $250,000 or more.

These projects must have a principal contractor, and the principal contractor must prepare a written WHS management plan before construction work starts.

The $250,000 threshold is about the cost of the construction work, not the overall value of the development or the value of a single subcontract.

What if your project is under $250,000?

A project under the threshold doesn’t trigger the WHS management plan requirement, but that doesn’t mean it’s exempt from WHS duties. Businesses still have to manage risks, provide safe systems of work and meet their duties under the WHS Act and Regulation.

SWMS are still required for high-risk construction work, whatever the size of the job.

Who Is the Principal Contractor?

The principal contractor is the person or business that commissions the construction project, unless another person or business is appointed principal contractor in writing.

The principal contractor has overall responsibility for managing and coordinating safety on the project. That includes:

  • Preparing the WHS management plan before work starts
  • Making sure workers know about the plan
  • Coordinating safety arrangements between contractors
  • Collecting and reviewing SWMS
  • Managing site-wide risks
  • Keeping the plan up to date
  • Keeping the plan available to workers

Bringing on subcontractors doesn’t take away their own WHS duties. Each business still has to manage the risks of its own work.

What Should Be Included in a WHS Management Plan?

SafeWork NSW sets out five things a construction project WHS management plan must include.

1. Health and Safety Responsibilities

The plan must list the names, positions and safety responsibilities of the people with safety roles on the project. For example:

  • Principal contractor: overall coordination of site safety
  • Site supervisor: daily site inspections and keeping an eye on the work
  • WHS coordinator: safety paperwork, inductions and compliance checks
  • First aid officer: first aid and emergency response

Clear roles mean workers know exactly who to go to when a safety issue comes up.

2. Consultation, Cooperation and Coordination

Most construction sites have several businesses working side by side. The plan must explain how they’ll consult, cooperate and coordinate their work. This could include:

  • Daily pre-starts
  • Toolbox talks
  • Contractor coordination meetings
  • Communication between site supervisors and subbies
  • How overlapping work is managed
  • How changes to site conditions are communicated

The aim is to stop one contractor’s work creating risks for another.

3. Managing WHS Incidents

The plan must explain how incidents will be managed, including:

  • How workers report incidents and hazards
  • Who responds
  • First aid and emergency arrangements
  • How incidents are investigated
  • Notifying SafeWork NSW when required
  • Corrective actions so it doesn’t happen again

Every worker should know what to do straight after an incident and who to call.

4. Site-Specific Health and Safety Rules

Every site has its own hazards and ways of working. The plan must set out the site rules and explain how everyone on site will be told about them. Examples include:

  • Required PPE
  • Site access and sign-in
  • Traffic management
  • Working at heights
  • No-go zones
  • Housekeeping and waste
  • Plant and equipment rules

Keep the rules practical and specific to the work happening on the job.

5. Collecting, Assessing, Monitoring and Reviewing SWMS

The plan must explain how SWMS will be collected, assessed, monitored and reviewed. This matters most where high-risk construction work is involved.

The principal contractor should have a process to:

  • Get SWMS before high-risk construction work starts
  • Check that each SWMS matches the work being done
  • Fit SWMS in with the overall site safety arrangements
  • Check that the controls are actually being followed
  • Review SWMS when the work or site conditions change

A SWMS shouldn’t just be collected and filed in the site office. Its controls need to be followed and checked while the work is happening.

WHS Management Plan Example: What Goes in Each Section?

Knowing what has to be included is one thing. Knowing how to write it is another.

Here’s a simple sample layout showing how the five required elements could be written up for a construction project.

This is an example layout only. It is not a completed plan for a real project.

Plan sectionWhat to includeExample wording
Project detailsSite address, project description and key contactsProject: [Project Name]. Address: [Site Address]. Principal Contractor: [Business Name].
Safety responsibilitiesNames, positions and responsibilities[Name], Site Safety Coordinator, [Phone]: runs daily pre-starts and checks site safety arrangements.
Consultation and coordinationContractor meetings and how information is sharedAll subcontractors attend scheduled coordination meetings and tell the site supervisor about changes to their work.
Incident managementReporting, emergency response and investigationReport all incidents immediately to [Contact Name]. Emergency arrangements are displayed in the site office.
Site-specific rulesSite access, PPE, traffic and other safety rulesAll workers must complete the site induction, wear the required PPE and use the marked pedestrian and vehicle routes.
SWMS arrangementsCollection, assessment and monitoringSWMS must be provided and reviewed before any high-risk construction work starts.

What Makes a Good WHS Management Plan?

A good plan is:

  • Specific to the job
  • Easy for workers and subbies to understand
  • Clear about who does what and how information is shared
  • Matched to the work actually happening on site
  • Backed up by site procedures and paperwork
  • Updated when the project or site conditions change

It should be detailed enough to explain how safety will be managed, without being more complicated than it needs to be.

WHS Management Plan vs SWMS vs Safety Management Plan

These terms often get mixed up, but each document does a different job.

DocumentWho prepares it?Main purposeWhen is it needed?
WHS management planPrincipal contractorManages site-wide safety arrangementsConstruction projects worth $250,000 or more in NSW
SWMSThe business doing the high-risk construction workSets out the high-risk work, hazards and controlsBefore high-risk construction work starts
Company-wide safety management planThe business or organisationSets out broader WHS policies and proceduresAs the business needs it to meet its WHS duties

What Is the Difference Between a WHS Management Plan and a SWMS?

A WHS management plan covers how safety is managed across the whole construction project. A SWMS covers one piece of high-risk construction work and sets out its hazards, risks and controls.

For example, the principal contractor on a commercial build might have a WHS management plan covering site access, contractor coordination, emergency arrangements and safety roles. A roofing subbie on the same job prepares a SWMS covering work at heights, roof access and fall prevention.

The two documents need to work together. For more, read our guides:

Keeping Your WHS Management Plan Current

Writing the plan before work starts is only the first step. The principal contractor must keep it current for the life of the project. Under NSW requirements, the principal contractor must:

  • Review the plan and update it when needed
  • Tell workers about changes that affect them
  • Make sure workers know what the plan says before they start work
  • Tell workers they have the right to read the plan
  • Keep the plan easy to get to for everyone doing construction work

The plan must be kept until the project is finished. If a notifiable incident happens on the project, it must be kept for at least two years after the incident.

When Should You Review the Plan?

Review the plan when:

  • New subcontractors start on site
  • Site conditions change
  • The work changes significantly
  • New hazards turn up
  • An incident or near miss shows a gap
  • Safety roles change
  • Existing controls aren’t working any more

For example, when a job moves from excavation to structural work, check whether the site rules, contractor coordination and SWMS process still fit.

Other Principal Contractor Duties on a NSW Construction Site

The WHS management plan is only one part of the principal contractor’s job. They also have to manage a range of site-wide safety matters.

Site Signage

The principal contractor must put up signs that can be seen from outside the site, showing:

  • The principal contractor’s name
  • A 24-hour contact phone number
  • Where the site office is

Amenities

Workers need proper amenities on site, kept in good order.

First Aid

First aid arrangements need to suit the type of work and the risks involved.

Emergency Plans

The site needs an emergency plan, including how to respond to emergencies that could reasonably happen.

Managing Site-Wide Risks

The principal contractor must also manage site-wide risks such as:

  • Storing and moving materials and waste
  • Plant and equipment
  • Traffic around the site
  • Essential services
  • Falling objects
  • Hazardous chemicals and atmospheres

These should all tie in with the WHS management plan and the work contractors are doing on site.

WHS Management Plan Pre-Start Checklist

Before work starts, use this checklist to make sure your WHS management plan covers the key requirements.

Project and responsibilities

  • Project details and site address recorded
  • Principal contractor details included
  • Safety personnel named, with their positions
  • Safety responsibilities clearly allocated

Consultation and coordination

  • Contractor communication arrangements set up
  • Pre-start and toolbox talk process written down
  • Process for coordinating overlapping work in place

Incident management

  • Incident reporting process written down
  • Emergency contacts available
  • First aid and emergency arrangements covered
  • Incident investigation and corrective action process in place

Site-specific rules

  • Site access requirements written down
  • PPE requirements set
  • Traffic and pedestrian arrangements covered
  • Site hazards and rules communicated to workers

SWMS management

  • Process for collecting SWMS written down
  • Process for checking SWMS in place
  • Monitoring and review arrangements in place
  • SWMS received before high-risk construction work starts

Communication and review

  • Workers told about the plan before they start work
  • Workers told they have the right to read the plan
  • Plan easy to get to on site
  • Process in place to review and update the plan
  • Changes communicated to the workers they affect

This checklist is a practical starting point, not a replacement for checking the full requirements for your project.

WHS Penalties and SafeWork NSW Notices

SafeWork NSW inspectors can act when safety rules aren’t followed. Depending on the situation, they can issue improvement notices, prohibition notices or penalty notices. More serious breaches can end up in court.

The NSW WHS Regulation 2025 added new penalty notice offences and increased some penalty notice amounts. For example, reported increases for companies include:

OffencePrevious amountNew amount
Failing to comply with an improvement notice$4,500$11,250
Failing to notify SafeWork NSW of a notifiable incident$7,450$12,500

These are penalty notice amounts, not the maximum court penalties for WHS breaches. Actual penalties depend on the offence and the circumstances.

Failing to prepare, maintain or communicate a required WHS management plan can also attract penalties.

The best approach is to get practical safety arrangements in place before work starts and keep them going for the whole job.

WHS Management Plans for NSW Government Construction Projects

NSW Government construction projects can come with extra WHS management requirements.

The NSW Government publishes separate WHS management guidelines for construction projects procured by government agencies. If you’re working on a government job, check the tender documents and those guidelines as well as your general WHS duties.

How SSOS’s Construction Safety Consultants Can Help

A WHS management plan that ticks the boxes is important, but making sure it works on site matters just as much.

At Solving Safety On Site (SSOS), we provide practical construction safety consulting to help businesses find gaps, improve their site safety systems and manage their WHS responsibilities.

Our approach is simple: what will work on site, not more paperwork.

We work with businesses right across the construction industry, including:

  • Builders and principal contractors
  • Subcontractors
  • Civil contractors
  • Crane and lifting businesses
  • Roofing contractors
  • Other high-risk trades

Our Construction WHS Consulting Services

WHS System Reviews

We review your WHS system and paperwork to find gaps, inconsistencies and room for improvement.

Site Inspections

We walk your site to spot safety issues and see how well your controls are working in practice.

Compliance Audits

We check your WHS arrangements against the requirements and show you where to improve.

Risk Management

We help you identify hazards, assess risks and put the right controls in place.

Corrective Action Support

We help you fix safety issues, respond to audit findings and improve your systems.

Project Safety Documentation

We help with project WHS documentation and safety requirements, including what builders and principal contractors need.

Everything we do is backed by hands-on construction experience.

Start With a Free WHS System Review

Not sure whether your WHS paperwork is up to scratch for your business or your next project?

SSOS offers a free initial WHS system review to find obvious gaps in your safety system, SWMS or other safety documents. We’ll tell you what’s working, what needs attention and the practical next steps.

Find out more about our construction safety consultants and how we can help your business.

Frequently Asked Questions About WHS Management Plans

Who prepares a WHS management plan?

The principal contractor prepares the written WHS management plan for a NSW construction project worth $250,000 or more. It must be done before construction work starts and should reflect the actual site, the work and the safety arrangements.

Is a WHS management plan required for projects under $250,000?

The WHS management plan requirement applies to projects where the construction work costs $250,000 or more. Smaller projects still have to meet general WHS duties, and a SWMS is still required for high-risk construction work.

What is the difference between a WHS management plan and a SWMS?

A WHS management plan explains how safety will be managed across the whole construction project. A SWMS sets out the hazards, risks and controls for a specific piece of high-risk construction work. They do different jobs and need to work together.

Who is the principal contractor?

The principal contractor is usually the person or business commissioning the construction project, unless another person or business is appointed in writing. The principal contractor coordinates site-wide safety and prepares the WHS management plan.

How often should a WHS management plan be reviewed?

There’s no set review period for every project. The principal contractor must review and update the plan as needed to keep it current, especially when site conditions, the work, safety roles or safety arrangements change.

Is there a WHS management plan template?

Yes, you can use a template as a starting point. But it must be tailored to your project and cover all the required elements. A generic template that doesn’t match the actual site and work won’t meet the requirements.

Need Help With Your WHS Management Plan?

Getting your WHS management plan sorted before the job starts sets clear safety roles, improves contractor coordination and reduces the risk of compliance problems.

Whether you’re a builder, principal contractor or subbie, SSOS can help you understand your WHS requirements and get your safety documentation right.

Need a WHS management plan written or audited before your project starts? Start with a free WHS system review from our construction safety consultants.

Visit SSOS Construction Safety Consulting to find out how we can help.

About the author

Solving Safety On Site (SSOS) provides practical work health and safety consulting for Australian construction businesses. Our services include WHS system reviews, site inspections, compliance audits, risk management and project safety documentation.